Moulamein roads, kerbs, gutters and footpath upgrades
Consultation has concluded
Moulamein Street Infrastructure Projects
As part of Council's Capital Upgrade Plan, we constructed a number of new footpaths in Moulamein.
What was involved?
The works include footpaths along Tallow and Turora Streets, and along Baratta Street with new footpath, kerb and guttering. There is also car parking facilities in front of the Medical facility building.
The red lines on the map below give an approximate indication of the works areas (not to scale).
We have also designed other kerb and guttering projects around town for works into the future.
Moulamein Street Infrastructure Projects
As part of Council's Capital Upgrade Plan, we constructed a number of new footpaths in Moulamein.
What was involved?
The works include footpaths along Tallow and Turora Streets, and along Baratta Street with new footpath, kerb and guttering. There is also car parking facilities in front of the Medical facility building.
The red lines on the map below give an approximate indication of the works areas (not to scale).
We have also designed other kerb and guttering projects around town for works into the future.
Lifecycle
Design
Moulamein roads, kerbs, gutters and footpath upgrades has finished this stage
Our project team will undertake comprehensive design works for the new footpath.
Request for Tender - October/November 2023
Moulamein roads, kerbs, gutters and footpath upgrades has finished this stage
Council will release the tender for construction works.
Construction - April/May 2024
Moulamein roads, kerbs, gutters and footpath upgrades has finished this stage
Construction is expected to commence in April/May. It will take around 6-8 weeks to complete.
Works complete- June 2024
Moulamein roads, kerbs, gutters and footpath upgrades is currently at this stage